The 700000 egg chicken breeding project in Pingtang County adopts advanced steel structure engineering methods and technologies, arranges construction time and resources reasonably, adheres to the enterprise tenet of "safety first, quality first, service first", and establishes an effective engineering quality management system. The company strictly implements the ISO9001 quality management system and implements procedural control and management for each process. The company has a first-class steel structure installation team with rich experience, fast construction speed, and good installation quality. The completed engineering projects are highly recognized and praised by customers. Shanghai Yizhu Agriculture and Animal Husbandry Technology Co., Ltd. adheres to the principle of "safety first, quality first, and service first", and insists on the premise of "pioneering and innovative, pursuing excellence, and striving for first-class engineering", providing customers with one-stop engineering services including design, manufacturing, and installation. Based on the concept of win-win cooperation, we aim to build more high-quality building projects that are full of beauty.
Conducted every morning, key tasks are deployed and emphasized to ensure that each team member is aware of them, and to facilitate cooperation among construction personnel. A summary of yesterday's construction situation and progress is made, and areas that need to be improved are further improved to achieve zero accidents and zero rework, and the construction site is cleared by personnel.
During the construction process, if the on-site layout is not reasonable and the materials are stacked in a disorderly manner, it will affect the construction progress. Through safe and civilized construction, it is possible to plan the site layout reasonably, ensure orderly stacking of materials, reduce unnecessary waste and delays, and thus improve construction efficiency.
Anti corrosion coating is an important measure to protect steel structures from corrosion, so steel entering the site should undergo anti-corrosion coating inspection, including coating thickness, adhesion, weather resistance (referring to the ability to withstand comprehensive damage caused by light, cold, wind, bacteria, etc.), etc. Ensure that the quality of the anti-corrosion coating meets the design requirements and improve the durability and service life of the steel structure.
This steel structure project has a tight schedule and a heavy task. The construction period is only 50 days. In order to ensure the smooth progress of the work, all the construction personnel rush to their posts during the Mid Autumn Festival to be responsible for their work. The management personnel maximize the construction efficiency, control the progress, adjust the plan in time, and ensure the completion of the project on schedule. This is a very big challenge for the construction personnel and management personnel on the site.
Construction drawing for installation of roof purlins
Construction drawing for installation of roof substructure
Construction drawing for installation of suspended ceiling substructure
Construction Drawing for Ceiling Panel Installation
Construction drawing for roof panel installation
Ceiling panel installation completion rendering
Effect diagram of completed installation of ridge cover plate
Completion rendering of roof panel installation
Before installing the enclosure panels, it is necessary to measure and locate the steel structure to ensure the accuracy of the installation position. According to the design requirements, use appropriate connection methods and fasteners to firmly install the enclosure panel on the steel structure. During the installation process, attention should be paid to protecting the board to avoid damage or deformation, while ensuring the flatness and verticality of the installation to meet the design requirements.
Ceiling insulation cotton laying effect diagram
Thermal insulation cotton can effectively reduce the temperature loss inside steel structure buildings, save energy, reduce energy consumption and emissions, and play a good role in maintaining indoor temperature.
Design rendering of completed installation of mountain wall panel
Exterior wall panel and exterior wall small window installation completion rendering
Aerial photo of project completion
The successful completion of the steel structure project, Yizhu Agriculture and Animal Husbandry would like to express sincere gratitude to all personnel involved in this project. Through everyone's joint efforts, we have successfully completed this challenging task. We will continue to adhere to the principles of quality first and safety first, strive to achieve sustainable development goals, and summarize experiences and lessons learned to continuously improve and enhance competitiveness, providing reference and inspiration for future projects.
Yizhu Agriculture and Animal Husbandry would like to express special thanks to the support and cooperation from the owner unit, supervision unit, audit unit, construction team, design team, and suppliers.